14 – 22 August, 2023

Coconut Lane Villa build progress | Part 2

 

Ready, set, go!

From the first day of building our Koh Phangan pool villa for sale, the construction crew set off at a cracking pace. This time we are working with a long-time friend as our subcontractor and (very) happily he has come through.

The concrete you see to the right is no ordinary concrete. It is the first concrete poured on site! Yay!

TBH building anywhere, and particularly in Koh Phangan, can be the best process or an absolute nightmare. Of course, this depends on the building team and communication. Luckily (not really as we have done our homework) our team has been great to work with.

Koh Phangan pool villa build progress - the pool sub base poured in part 1

Follow our Corner Cottages Koh Phangan Villa construction

Follow us and our progress with our construction and come along for the ride. We hope that we can demystify some of the gossip that we only too often hear floating around the Koh Phangan communities. You can see the construction progress as it unfolds and evolves from a few holes in the ground to a fully finished Koh Phangan pool villa ready for enjoying (or buying!).

Koh Phangan pool villa for sale first two weeks progress

So what was achieved in the first 2 weeks of our Koh Phangan construction?

I think it’s easiest to make a summary list for you to see >>>>

So, not bad I think.

See the photos below

  • The pool concrete sub-base poured
  • The pad of the footing’s steel prepared
  • The footing’s columns steel prepared
  • The first column (house) blessed in a traditional ‘Sao Ek’ Thai ceremony
  • Concrete poured for both footing pads and footing (GFB) columns
  • The Pool base poured with plumbing in place
  • The pool wall’s steel reinforcement prepared and shuttered
  • The pool wall’s concrete poured

So far so good. The great progress in our build will continue, and we will update you as we go along the way.

The next stage is to back-fill the footings and pool voids and then the work on the ground floor beam can begin.


Stay tuned for our next exciting instalment of our Koh Phangan villa for sale construction process!